Port Credit Outdoor Pool Redevelopment
Funding Project
RInC Funded Project
Project
Port Credit Outdoor Pool Redevelopment
Drawings
Port Credit Outdoor Pool
Redevelopment
Construction Photos
Port Credit Pool
Status as of
December 2011
Information below is current as of the date identified. Information, including the date and
status for each phase may change throughout the project. Updates will be posted once a
month.
| Phase |
Date |
Status |
| Consultant awarded |
July 2009 |
Complete |
| Program development |
July 2009 |
Complete |
| Design development |
October 2009 to
December 2009 |
Complete |
| Site plan approvals |
November 2009 |
Complete |
| Design sign-off |
December 2009 |
Complete |
| Contractor tender |
February 2010 |
Complete |
| Contractor awarded |
April 2010 |
Complete |
| Construction start |
April 2010 |
Complete |
| Construction completion |
May 30, 2011 |
Complete |
| Open to the public |
June 17, 2011 |
Complete |
| Official opening event |
July 10, 2011 |
Complete |