City Centre Transit Terminal Infrastructure Renovation

The City Centre Transit Terminal is undergoing a complete interior renovation that is expected to be completed by fall 2021.

Once construction is complete, the terminal will transform into a modernized space with improved accessibility and service for MiWay customers.

Customers can access the terminal during renovations, including the new Fares booth that is now open and are encouraged to visit this page for project updates.

MiWay staff will continue to be onsite in order to serve you. Please look out for signage with temporary access points during these renovations.

 

Construction details

The terminal was built in 1996 and is 23 years old. It requires facility upgrades to meet the growing and changing needs of our community.

Below is a summary of the renovation work and the expected construction timelines.

Scheduling is subject to change.

City Centre Transit Terminal counter

The new Fares Booth inside City Centre Transit Terminal.

Newly renovated booth with information sign next to stairway, inside CCTT station

The new Information Booth inside City Centre Transit Terminal.

Renovation work Construction begins Status update
Demolition Winter 2019 In progress
North Entrance Winter 2019 In progress
Fares Booth Winter 2019 Completed on Oct. 20, 2020
Upper level flooring Winter 2019 Completed
Staff washrooms Spring 2020 Completed on Sept. 23, 2020
Staircase Fall 2020 In progress
Elevator Fall 2020 Completed on Jan. 6, 2021
Lower-level flooring Fall 2020 In progress
South Entrance (lower level to Square One) Fall 2020 In progress
Supervisor Booth Fall 2020 Completed on Dec. 8, 2020
Escalator Fall 2020 In progress
Information Booth Fall 2020 Completed on Jan. 22, 2021