Description: Bough Beeches Boulevard, from Fieldgate Drive to Claypine Rise

Status: Completed 2018

Documents:

Description: Brandon Gate Drive, from Netherwood Drive to Darcel Avenue

Status: Completed 2020

Documents:

Description: Cambrett Drive, from Morning Star Drive to Etude Drive

Status: Approved – Construction Pending 2021

Documents:

Description: Council Ring Road, from Glen Erin Drive (south intersection) to The Collegeway

Status: Approved – Construction Pending 2021

Documents:

Description: Credit Valley Road, from Winston Churchill Boulevard to Erin Mills Parkway

Status: Completed 2019

Documents:

Description: Edenwood Drive, from Battleford Road to Ganymede Road

Status: Completed 2014

Documents:

Description: Erin Centre Boulevard, from Tenth Line West to Ninth Line

Status: Completed 2019

Documents:

Description: Falconer Drive, from Matlock Avenue to Kenninghall Boulevard

Status: Approved – Construction Pending 2021

Documents:

Description: Fieldgate Drive, from Bough Beeches Boulevard to Ponytrail Drive

Status: Completed 2018

Documents:

Description: Fifth Line West, from Dundas Street West to South Millway

Status: Completed 2014

Documents:

Description: Flagship Drive, from Rymal Road to Queen Frederica Drive

Status: Completed 2021

Documents:

Description: Galesway Boulevard, from Whitehorn Avenue to Terry Fox Way

Status: Recommended, Councillor Approval pending

Description: Galesway Boulevard, from Whitehorn Avenue to Terry Fox Way

Status: Recommended, Councillor Approval pending

Description: Golden Orchard Drive, from Willowbank Trail to Rathburn Road East, and from Burnhamthorpe Road East to Bloor Street

Status: Approved – Construction Pending 2021

Documents:

Description: Havenwood Drive, from Gulleden Drive to Fieldgate Drive

Status: Completed 2019

Documents:

Description: Homelands Drive (entire roadway)

Status: Completed 2018

Documents:

Description: Huntington Ridge Drive, from Winfield Terrace to Kingsbridge Garden Circle

Status: Completed 2014

Documents:

Description: Lisgar Drive, from Doug Leavens Boulevard to Beacham Street

Status: Completed 2020

Documents:

Description: Lorne Park Road, from Truscott Drive to Birchwood Drive

Status: Completed 2019

Documents:

Description: Metcalfe Avenue (entire roadway)

Status: Completed 2019

Documents:

Description: Montevideo Road, from Glen Erin Drive to Aquitaine Avenue

Status: Completed 2020

Documents:

Description: Novo Star Drive, from Mavis Road to McLaughlin Road

Status: Recommended, Councillor Approval pending

Description: Osprey Boulevard, from Waxwing Drive to Snowflake Lane

Status: Completed 2020

Documents:

Description: Paisley Boulevard West, from Huron Park to Confederation Parkway

Status: Approved – Construction Pending 2021

Documents:

Description: Perran Drive (entire roadway)

Status: Completed 2018

Documents:

Description: Redstone Road (entire roadway)

Status: Completed 2020

Documents:

Description: Second Line, from Old Derry Road to North Limit of Roadway

Status: Completed 2015

Documents:

Description: Second Line West, from Sombrero Way to Old Derry Road

Status: Approved – Construction Pending 2021

Documents:

Description: Silvercreek Boulevard (entire roadway)

Status: Pending approval

Description: Sombrero Way, from Second Line West to Mavis Road

Status: Approved – Construction Pending 2021

Documents:

Description: Tacc Drive, from Tenth Line West to Freshwater Drive

Status: Completed 2020

Documents:

Description: Thornlodge Drive (entire roadway)

Status: Completed 2018

Documents:

Description: Twain Avenue (entire roadway)

Status: Completed 2019

Documents:

Description: Queen Street West, from Lorne Park Road to Shawnmarr Road

Status: Recommended, Councillor Approval pending

Description: Westbridge Way (entire roadway)

Status: Completed 2017

Documents: