In progress City project

City Centre Transit Terminal Infrastructure Renovation

The City Centre Transit Terminal is undergoing a complete interior renovation that started in winter 2019 and is expected to be completed by fall 2021.

Once construction is complete, City Centre Transit Terminal will transform into a modernized space with improved accessibility and service for MiWay customers.

Customers can access the terminal during renovations, including the new Fares and Information booths that are now open.

MiWay staff will continue to be onsite in order to serve you. Please look out for signage with temporary access points during these renovations.

Construction details

The terminal was built in 1996 and is 23 years old. It requires facility upgrades to meet the growing and changing needs of our community.

Below is a summary of the renovation work and the expected construction timelines. Scheduling is subject to change.

Renovation work Status
Demolition In progress
Staircase In progress
Lower level flooring In progress
South Entrance (lower level to Square One) In progress
Escalator In progress
North Entrance Completed
Fares Booth Completed
Information Booth Completed
Upper level flooring Completed
Staff washroom Completed
Elevator Completed
Supervisor Booth Completed