Background
M City will be a mixed-use community that will transform the area into a dense urban space that is vibrant, walkable, and livable. The first two towers, M1 and M2, will be 61 storeys while the tallest tower, M3, will reach 81 storeys.
Construction began in 2019 and is occurring in phases. Planning for future phases is also underway.
Key facts
M City is designed to fit into the Downtown21 Master Plan and will be a significant new mixed-use community in the city centre. This community will become the western gateway to Downtown Mississauga and compliment the Absolute Towers at the eastern gateway. The M1 and M2 towers will surpass the tallest buildings in Mississauga, while the M3 tower will be one of the tallest in the GTA at 81 storeys
Project highlights:
- More than 5,000 new residential units
- Attract more than 10,000 new residents
- 39,000 square feet of retail space in Phase 1
- 2 acres of parkland in Phase 1
-
1June 2014
M-City unveiled
-
2April 2015
Master Site Plan Application approved
-
3Early 2019
Construction to begin on first phases
-
4March 2019
Council decision to remove ‘H’ holding for Phase 1
-
52022
Planned occupancy for M1 tower and M2 tower
-
6Spring 2023
Expected completion of M3 tower
-
72023+
Planning for future phases continues