Current updates
October 2025
General Contractor
- All general contractor work is done.
- The project is currently in its warranty period and will be monitored during this time.
City Forestry work
- The planting of the remaining trees will start at the end of October 2025, weather permitting
- Remaining median planting along Rathburn Road East (cul-de-sac) to be completed in Spring 2026
September 2025
Work completed by General Contractor
- Soil remediation within the boulevards along Rathburn Road East (dead-end section)
- Sod restoration
- Concrete pad modification and installation of bike racks
Work to be completed by City Forestry
All plantings, including tree and median plantings to be completed in Fall 2025
August 2025
The project is substantially complete. At this stage, you may see the contractor on site from time to time addressing deficiencies, completing final restoration works and preparing for final landscape completion. This is typical of all construction projects. Any work identified as deficiencies is performed at no additional cost to the City.
Work being completed by General Contractor
- Soil remediation within the boulevards along Rathburn Road East (dead-end section)
- Sod restoration
- Concrete pad modification and installation of bike racks
The General Contractor is scheduled to address all deficiencies by the end of August, weather permitting. As hot, dry temperatures are not conducive to sod installation, sod is required to be installed during cooler temperatures.
Work to be completed by City Forestry
- All plantings, including tree and median plantings
Forestry is scheduled to start the planting work in September once the weather is more conducive to planting.
Past updates
December 2024
Completed work
- Roadworks, including asphalt paving
- Installation of bus shelter pads and bus-stop platforms
- New traffic signals and new streetlights are activated and functional
- Installation of concrete sidewalks and median islands
- Installation of noise walls
- Installation of culvert
- Most of the restoration works
Ongoing work
- Installation of the remainder of topsoil and sod
- Planting within the median planters and at the intersection of Ponytrail Drive and Rathburn Road East
- Installation of the remainder of the bus shelters
- Installation of bike racks
- Tree planting within in the project limits
- Installation of the remainder of the pavement markings for the cycle tracks
- Deficiencies
September 2024
Completed work
- Installation and activation of streetlights between Dixie Road and Burnhamthorpe Road
- Installation and activation of traffic signals at Bough Beeches Boulevard, Rockwood Road, Fieldgate Drive, Off Road Trail 11 (Hydro Corridor) and Shaver Trail
- Installation of noise walls
- Installation of culvert pipe
- Installation of storm sewer appurtenances between Dixie Road and Burnhamthorpe Road
- Construction of bus shelter pads
Ongoing work
- Final layer of asphalt paving on roadways and cycle tracks along Rathburn Road East and Ponytrail Drive
- Concrete sidewalk installation between Dixie Road and Ponytrail Drive
- Road and boulevard work on Rathburn Road East, from Ponytrail Drive to the east limit
- Installation of MiWay bus shelters
August 2024
Completed work
- Culvert pipe installation
- Base asphalt paving between Dixie Road and Burnhamthorpe Road
- Streetlight installation between Dixie Road and Fieldgate Drive
- Noise wall installation
Ongoing work
- Traffic signal installation at Bough Beeches Boulevard, Rockwood Road and Fieldgate Drive is complete but still need to be energized (expected shortly)
- Storm sewer appurtenances/catch basins at Rathburn Road East cul-de-sac
- Roadworks at Rathburn Road East from Ponytrail Drive to the east limit
- Construction of cycle tracks, bus pads and sidewalks
- Erosion protection work related to the culvert
May 2024
Completed work
Culvert pipe installation has been completed.
Ongoing work
The following construction on Rathburn Road is underway:
- Curb and gutter construction
- Cycle track construction
- Noise wall installation on both sides of Rathburn Road
- Traffic signals installation
- Street lighting installation
- Catch basin relocation (work is almost complete)
New work beginning
Road rehabilitation work from Dixie Road to Burnhamthorpe Road East will begin the last week of May. It will be completed in stages, as shown in the construction phasing plan, and will include:
- Grinding of existing asphalt pavement
- Placement of granular material
- Paving of base asphalt
January 2024
Construction is advancing as planned. Most of the boulevard work between Dixie Road and Fieldgate Drive has been completed. This includes:
- Curb installation
- Electrical conduits installation
- Driveway apron replacements
- Boulevard grading to accommodate the new cycle tracks
- Sidewalk replacements
The construction phasing plan for the entire project includes:
- Construction activity on Rathburn Road East, from Dixie Road to Fieldgate Drive, between Q4 2023 and Q2 2024
- Noise wall installation at the intersection of Rathburn Road East and Fieldgate Drive between Q1 2024 and Q2 2024
- Replacement of the culvert crossing over Etobicoke Creek between Q1 2024 and Q2 2024
- Construction activity at the intersection of Rathburn Road East and Fieldgate Drive in Q2 2024
- Construction activity on Rathburn Road East, from Fieldgate Drive to Burnhamthorpe Road, between Q2 2024 and Q4 2024
- Construction activity at the intersection of Rathburn Road East and Ponytrail Drive in Q4 2024
- Construction activity on Rathburn Road East, from Ponytrail Drive to cul-de-sac, between Q2 2024 and Q4 2024

The construction phasing plan is tentative and may change due to weather and unforeseen factors.
October 2023
Construction of the Rathburn Road and Ponytrail Drive Integrated Road Project has commenced.
August 2023
Noise wall installation has been completed along Ponytrail Drive from Rathburn Road East to Burnhamthorpe Road.
January 2023
Noise wall installation has started along Ponytrail Drive from Rathburn Road East to Burnhamthorpe Road.