Don McLean Westacres Outdoor Pool

Funding
Community Infrastructure Improvement Fund (CIIF)
City of Mississauga Capital Budget

Estimated Cost
$4.6 million

Architect
Moffet and Duncan Architects Inc.

Contractors
PCL Constructors Canada Inc

Background
According to the City of Mississauga's Strategic Plan, one of the City's strategic goals is to build and maintain its infrastructure for its citizens for generations to come. Sound, functional and attractive buildings, facilities, roads, transit, public and open spaces are integral to completing our neighbourhoods as we build a City for the 21st century.

Don McLean Westacres Outdoor Pool is 47 years old and serves approximately 85,000 residents and is the last of the City’s outdoor pools to be redeveloped. Construction will update the pool’s mechanical systems to increase its lifecycle, efficient use of energy and water, and improve accessibility for residents of all ages.

Objectives/Benefits
Reinvesting in the redevelopment of the existing outdoor pool and building will significantly expand the outdoor pool’s lifespan, and will include:
* Updating facility change rooms and washrooms
* Replacing the pool tank
* Bringing the facility to Accessibility for Ontarians with Disabilities Act (AODA) standards
* Providing two barrier-free parking spaces
* Upgrading site services
* Replacing the pool deck

This investment will generate a number of benefits for the community with enhancements that will include:
* Improved energy efficiency
* Reduced water consumption by replacing pool tank and filtration system
* Better accessibility
* Shaded area for pool users
* Increased use by area residents due to the facility's new, modern and appealing visual and functional design

The community has committed to raise funds towards the project.

For a glimpse of the project drawings, please click on the link below

Don McLean Westacres Outdoor Pool