Don McLean Westacres Outdoor Pool Updates

Funding Program
CIIF Funded Project

Drawings
Project Drawings

Status as of
December 2013

Information below is current as of the date identified. Information, including the date and status for each phase may change throughout the project.

Phase

Date

Status

Consultant sourced

Jan. 2013

Completed

Construction manager sourced

Jan. 2013

Completed

Program development

Feb. 2013

Completed

Schematic design

Feb. 2013

Completed

Design development

Mar. 2013

Completed

Site plan approval

Aug. 2013

Completed

Tendering

Oct. 2013

Completed

Construction start

Mar. 2013

Completed

Construction completion

March 2014

On Schedule

Open to the public

Summer 2014

On Schedule

Official opening event

TBC

To Follow

Link to Construction Photos

For details on this project including project locations please see Project Backgrounders.

 