Information below is current as of the date identified. Information, including the date and
status for each phase may change throughout the project. Updates will be posted once a
month.
Phase
Date
Status
Consultant RFP
July 2009
Complete
Architect interviews
July 2009
Complete
Consultant award
July 2009
Complete
Design development
July to November 2009
Complete
Contract tender
February 2010
Complete
Contract award
March 2010
Complete
Library Closure (Lakeview)
February 7, 2010
Complete
Library Closure (Lorne Park)
February 14, 2010
Complete
Library Closure (Port Credit)
February 21, 2010
Complete
Construction start
(Lakeview)
March 2010
Complete
Construction start
(Lorne Park)
March 2010
Complete
Construction start
(Port Credit)
March 2010
Complete
Construction completion (Lakeview)
May 30, 2011
Complete
Construction completion (Lorne Park)
May 30, 2011
Complete
Construction completion (Port Credit)
May 30, 2011
Complete
Open to the public (Lakeview)
February 15, 2011
Complete
Open to the public (Lorne Park)
March 28, 2011
Complete
Open to the public (Port Credit)
March 15, 2011
Complete
Official opening event (Lakeview)
June 11, 2011
Complete
Official opening event (Lorne Park)
June 11, 2011
Complete
Official opening event (Port Credit)
June 11, 2011
Complete
For details on this project including project locations please see Project Backgrounders (Lakeview, Lorne Park, Port
Credit).