Streetsville Main Street Square Updates

Funding Program
CIIF Funded Project

Drawings
To follow

Status as of
August 2013

Information below is current as of the date identified. Information, including the date and status for each phase may change throughout the project.

Phase

Date

Status

Consultant sourced

Dec. 2012

Completed

Program development

Feb. 2013

Completed

Schematic design

Feb. 2013

Completed

Design development

April 2013

Completed

Tendering

June 2013

On Schedule

Construction start

Phase I
Phase II

 

July 2013
Spring 2014

 

On Schedule
On Schedule

Construction completion

Phase I
Phase II

 

Summer 2013
Summer 2014

 

Phase I complete
On Schedule

Open to the public

TBC

To follow

Official opening event

TBC

To follow

 


For details on this project including project locations please see Project Backgrounders.